| |
September
2004 Job Profiles
|
PFIZER CLINICAL RESEARCH LABORATORY |
| |
 |
|
Erection
Crew at Pfizer Clinical Research Laboratory “Tops
Out” without a hitch. |
|
|
MID ATLANTIC PROJECTS |
| |
 |
|
Bass
Pro Shop in Harrisburg (PA 1723) |
| |
|
|
 |
|
East
Lobby for 440 North Broad Street (PA 1702) |
|
April
2003 Job Profile
|
LAWRENCE APARTMENTS, PRINCETON UNIVERSITY |
| |
 |
|
The
Lawrence Apartments project consists of seven new buildings
ranging from 3 to 8 stories. Henderson Construction from
Raritan, New Jersey is the General Contractor. J.L. Erectors
is erecting, FEI is fabricating the structural steel detailed
by BSCC, and Sharon Stairs was specified as the pre-designed
stair manufacturer. |
| Our
portion of the project includes structural steel for three
of the buildings, penthouse framing for six of the buildings,
and miscellaneous metals for the entire seven. Four of
the buildings are block and plank construction and the
three structural buildings are steel and plank. The structural
steel portion is a unique design called "Girder Slab"
construction. The total square footage of the structural
portion is 127,000; the weight is approximately 452 tons
and there are 14 stair towers. |
| |
|
|
 |
|
The
appeal to using the "Girder Slab" construction
is definitely the schedule. We were originally going to
erect two of the six story buildings simultaneously but
due to weather and site conditions we only had two cranes
on the project for one week. The first two buildings were
hung and planked in 4 weeks. Included in that duration
were 5 days of down time |
due
to bad weather. So, the total erection days really only
amounted to 17 days. The third building was started
on March 24th and is the tallest of the three at 7 stories.
The erection duration for this portion is approximately
three weeks. Henderson Construction couldn't be much
happier with the performance. It really has been an
extraordinary effort by all parties involved thus far.
Girder
Slab construction is the first system to use precast
slabs with an integral steel girder to form a monolithic
structural slab assembly. The girder slab system consists
of an interior girder known as an open-web dissymmetric
beam or D-beam, supporting precast prestressed hollow
core slabs on its bottom flange. Upon grouting, the
Girder-Slab System develops composite action enabling
it to support residential live loads. Grouting is easily
achieved after slabs are set in place. The Girder-Slab
System affords users advantages never before available
with cast-in-place concrete superstructures. Headed
by Dave Kelting, our detailing department stepped up
to the challenges of learning the system and providing
the shop and field with the required information to
stay efficient and effective in completing the project.
|
| |
|
|
 |
|
From
preplanning the construction to erecting the last stair,
the success of the project, Lawrence Apartments at Princeton
University, has been a by-product of teamwork. The detailers
deserve high praise for clear, precise information.
Compliments to the crew at FEI for their craftsmanship
and to the men who did an outstanding job erecting.
"The fabrication was excellent and the steel fit
great," said Dave Mullens of J.L. Erectors.
Reported by Dennis Bachman, Mid-Atlantic Office
|
| |
|
 |
|
|
December
2002 Job Profile
UCONN
FOOTBALL STADIUM
Miscellaneous Metals Portion of Rentschler Field |
| |
 |
|
As
we entered the month of December, the UCONN Football Stadium
was 80%
complete and ahead of schedule for its August 30, 2003
opening. The
horseshoe shaped open air facility is situated on 75 acres
at the former
Pratt & Whitney Rentschler Airfield. |
| |
|
|
|
It has a seating capacity of 40,000, expandable to 50,000.
There are also 1,300 indoor club seats and 38 luxury suites
located within the Press Tower. The structural steel Press
Tower, which stands more than 100 feet above the playing
field, has two, 174 riser stairs at the east and west
ends. This work has been completed since September. The
more than three miles of perimeter guardrail and 524 aisle
rails are 90 percent complete and will be finished by
the end of January 2003. 152 Powder coated aluminum rails
within the tower will provide some indoor work during
the winter. |
| |
|
|
 |
|
There
are 44 sets of vomitory stair rails that access the seating.
This work was delayed because of code differences between
Ellerbe Becket (the architect) and the Connecticut State
Building inspectors. With concessions made by both parties
we can now expect this material at the jobsite in late
January 2003. |
| |
|
|
The
10 foot high ornamental fences and gates at five locations
is the means of fan access to the stadium. Thanks to Ben Padilla
for his design and development of a complex situation, this
material is now in production, has a scheduled delivery of
early March and will be completed in late April.
There
are also 30 sets of removable aluminum stairs that will provide
access from the low level seating to the playing field. A
mock-up of this was delivered to the job on December 16th.
Berlin
Steel has also been contracted to furnish and install the framing
for and the installation of the large screen, state of the art
video matrix scoreboard.
The Berlin Steel erection team, headed by Superintendents Mike
Guay and Jeff Miller, need to be commended for their outstanding
performance in coordinating and overcoming various adverse situations.
From the detailing aspect, Tom Godbout and his staff at Ocean
State have done an outstanding job resolving a multitude of
changes and challenges turning this into a successful project.
Finally,
we would like to wish success to UCONN coach Randy Edsall, his
players and staff as they enter their second season of Division
IA College Football. "Go Huskies"!!!!
Reported by Ray Baran, Project Manager/Miscellaneous Estimator
|
November
2002 Job Profile
| BERLIN
STEEL OFFICE EXPANSION UPDATE |
| |
 |
|
The current
offices of The Berlin Steel Construction Company were
constructed in 1965. A first addition was added in 1972,
and a second edition followed 10 years later in 1982.
Modular buildings were added in 1996 to temporarily handle
our need for additional space. |
In 2002, twenty years after the second addition, Berlin
Steel is undertaking our third permanent addition to the
original office building. The new addition will handle
the additional staff in our Estimating and Drafting departments,
as well as future staffing needs of the company.
The modular buildings have been relocated, the footings
and foundation walls are in, and steel erection began
on September 30th. Final completion is just around the
corner in 2003.
Reported
by Bob Smith, Office Expansion Project Manager
|
|
July 2002 Job Profile
| CONNECTICARE,
FARMINGTON, CT |
| |
 |
|
ConnectiCare
chose the Farmington location (Route 6 near the intersection
of New Britain Avenue and I-84) because of its close proximity
to their current location on Batterson Park Road, also
in Farmington. This new 100,000 sq. ft. facility will
house its customer service and technology center. |
Tomasso Group is handling the general construction of
this building, which is among the largest office buildings
currently under construction in the state of Connecticut.
Berlin Steel furnished 462 tons of structural steel, together
with 43 tons of deck/joist. The actual dimension for the
3-story building is 350 feet long by 105 feet wide. Site
conditions were favorable for erection - open site for
easy crane access.
The job was detailed and fabricated by B.K. Iron Works
of Quebec, Canada. Our customer was Casle Corporation.
The Project Manager was Bill Wadsworth and the Site Superintendent
was Mike McInerney. The Architect/Engineer was Kaestle
Boos Associates, Inc. Pat Sayers was the Field Foreman
for Berlin Steel.
This was another fast track project by Berlin Steel that
came in onschedule, without compromising quality or safety.
Congratulations to all!
Reported by Jim Wilson, Project Manger |
|
BRADLEY
AIRPORT NEW CONCOURSE & TERMINAL
| Congratulations
to the entire Berlin Steel Team on the highly successful completion
of this very significant and challenging project. |
| |
|
|
 |
| |
|
|
| |
|
|
|
From
Estimating, Bidding and Contract Negotiations, through Planning,
Detailing and Purchasing, to Erection, this complex project
was performed on time with the professionalism and attention
to safety that has become a hallmark of Berlin Steel over
its long history.
Particular
accolades go to Mario DeRoia, Drafting Manager, Don Ouelette,
the General Foreman for the Concourse, and Pat Sayers, the
General Foreman for the Terminal.
|
| |
|
|
 |
|
We
are pleased to have been a key participant in the development
of thisimportant project. The final product is an impressive
building, that as we frequent the airport over the coming
years, the participants can look backand be proud of the accomplishment.
Reported
by Mike Belcher, Project Manager
|
| |
|
 |
|
| |
|
|
|
| RENTSCHLER
FIELD PROJECT FOR THE UCONN FOOTBALL STADIUM
On
Monday February 25, 2002 we conducted a Topping Out ceremony
to celebrate the successful completion of the steel erection
phase of the 1,000 ton UCONN Football Sadium Pressbox.
This
marked an important milestone in the progress of the 40,000-seat
stadium which is scheduled to open with the start of the fall
football season in 2003. The event was attended by over two
hundred people including dignitaries representing national,
state, and local government, the UCONN Athletic Department,
members of the football team, Hunt/Gilbane, and the other
contractors.
UCONN
football coach Randy Edsall spoke expressing his gratitude
to the ironworkers and his pride in the new state-of-the-art
facility. Seven UCONN football players attended and signed
the topping-out beam.
Mike Belcher congratulated the entire erection team and especially
Mike Guay, our field superintendent, and Bianca D'Avignon,
the detailing job captain. He wished Coach Edsall and his
team success in the many years of big-time college football
to come at the University of Connecticut.
Reported
by Mike Belcher, Project Manager
|
|
|